The office building for the Ministry of Social Development and Human Security is a 29-storey high building with the usable area of 65,500 sq.m.
The service provided is the detailed design of the following systems :
- Structural design of the 120 m. high building, the main structural components are reinforced concrete with post-tensioned floor system.
- Sanitary and Fire Protection Systems comprising :
- An underground water tank with 600 cu.m. capacity.
- A wastewater treatment plant with 180 cu.m./day capacity.
- The fire protection system consists of wet riser standpipes and fire hose cabinets with 2 diesel fire pumps.
- Mechanical, Air Conditioning and Ventilation Systems comprising :
- The centralized chilled water system at 1,400 tons capacity.
- The pressurized system for stairwells and lobby.
- 10 sets of passenger and trade lifts.
- Electrical and Communication Systems
- The power distribution system with 4-1,600 kVA transformers.
- A standby generator at 800 kW.
- The lighting system, fire alarm system, telephone / sound system.
- The closed circuit television system.
- The master antenna television system, lightning protection system.
|