Layout of Water Treatment Plant, capacity 5,000 cu.m./hr.
 |
Water Supply system in the expansion area,
capacity 2,000 cu.m./hr.

|
|
Project Location |
: 229 Sukhumwit Rd., Amphoe Muang, Rayong |
Client |
: Thai Petrochemical Industry Public Company Limited |
Project Duration |
: 10 May 1996 to 10 Jan.1997 |
Construction Cost |
: 180.0 Million Baht |
Service Fee |
: 3.21 Million Baht |
|
Project Description |
Water supply system of Thai Petrochemical Industry Public Co., Ltd. located on Amphoe Ban Kai in Rayong Province, which is completely constructed with a capacity of 3,000 cu.m./hr. This project will be constructed the expansion of water supply system, with a capacity of 2,000 cu.m./hr. in the specific area.
PTC has designed the existing water supply system and was selected to carry out the expansion of the water supply system project.
Design and construct of the water supply system expansion with a capacity of 2,000 cu.m./hr. in TPI filtration Plant at Ban Kai, Rayong. Total capacity of the water supply system is to 5,000 cu.m./hr. which directly impacts on the components of the existing water supply system design and construction, for example, raw water, disinfection and sludge treatment. Therefore, PTC has studied, designed, improve the components of the existing water supply system for the increasing of the water supply system expansion for the effectiveness of the components of the Filtration Plant. |
|