Detailed Design of Water Treatment Plant with capacity of not less than
12,000 cu.m./day (Beer Thip Brewery (1991) Co., Ltd.)

Water Treatment  Plant : Capacity 12,000 cu.m./day



Project  Location : Bangban, Phra Nakhon Si Ayuthaya
Client : Beer Thip Brewery (1991) Co.,Ltd.
Project Duration : 1 Sep 2004 – 5 Aug 2005
Construction Cost : 123.50 Million Baht
Service Fee : 1.67 Million Baht
 
Project Description

The services provided include the detailed design of the following system.

- Detailed design Work

  • Water Treatment Plant
  • Capacity : surface water 12,000 cu.m./day
  • Source of Water : Noi River
  • Clear Water Tank with capacity of 1,000 cu.m.
  • Main Distribution system

- Preparation of Tender Document, Cost Estimation

- Instruction for tender evaluation

- Recommend for machine and equipment selection

Image Gallery Scoce of Services Contact Us
       For each of the field of activities, the PTC provides
a complete range of consulting services as summarized below

Reconnaissance Survey.
Field Investigations.
Study and Planning.
Engineering and Design.
Supervision, Engineering Advice and Construction Management.
Training and Guidance.
address :


Tel :

FAX :
E-mail :
Website :

12/14-15 Pathumwan Place condominium,
Soi Kasaemsan 1 Rama 1 Rd. Patumwan,
Bangkok 10330.
0-2214-3810,0-2215-2748,0-2215-3870-1
0-2216-46130-2612-3080-3
0-2216-6287
main@progress.co.th
www.progress.co.th

Copyright @ 2014 Progress Technology Consultants Co.,Ltd. All right reserved.
Progress Technology Consultants Co.,Ltd.