Activated Sludge Process, capacity 8,400 cu.m./day
 |

|
|
Project Location |
: Tambon Bo Win, Amphoe Sriracha, Chonburi |
Client |
: Eastern Industrial Co.,Ltd. |
Project Duration |
|
Design |
: June 1990 to Mar. 1991 |
Construction |
: Sept. 1990 to May 1992 |
Construction Cost |
: 96.0 Million Baht |
|
Project Description |
Chonburi Industrial Estate (Bo Win) locates in Tambon Bo Win, Amphoe Sri Racha, Chonburi, at km. 92 of national highway no. 331. This project area is approximately 1,500 rais (240 ha.)
The services provided include :
- Detailed design of Wastewater Treatment Plant
- Wastewater treatment plant is activated sludge system with a capacity of 12,000 cu.m./day. Primary treatment system consists of automatic screen, pumping station, grit chamber, equalization tank and neutralization tank. Secondary treatment system consists of aeration tank, sedimentation tank and chlorine contact tank. Sludge treatment system consists of sludge thickener and sludge dewatering system.
Construction of this plant was started in September 1990 and finished in May 1992. Total period of consturction is about 21 months.
Progress Technology Consultants Co.,Ltd. took responsibility in design, construction supervision and starting up of the wastewater treatment plant. |
|